Road 47, Hódmezővásárhely bypass section

Design services

UTIBER performed general design works for the 12.7-kilometre-long, 2×1-lane road section with design parameters that allow a speed limit of 110 kph. The most spectacular element of the project is undoubtedly the multi-level roundabout erected at the terminal interchange: the circular bridge near Kopáncs is composed of nine distinct units, and is the largest structure of its kind in Hungary.

12,7 km long

2×1lanes

6 interchanges

13 000 m³ structural concrete (circular bridge)

4 structures (circular bridge)

 

 

330 t structural steel

 